¶ 6.22.06 Drawings Objected to, Reference Numbers Not in Drawings
The drawings are objected to as failing to comply with 37 CFR 1.84(p)(5) because they do not include the following reference sign(s) mentioned in the description: [1]. Corrected drawing sheets in compliance with 37 CFR 1.121 (d) are required in reply to the Office action to avoid abandonment of the application. Any amended replacement drawing sheet should include all of the figures appearing on the immediate prior version of the sheet, even if only one figure is being amended. Each drawing sheet submitted after the filing date of an application must be labeled in the top margin as either "Replacement Sheet" or "New Sheet" pursuant to 37 CFR 1.121(d). If the changes are not accepted by the examiner, the applicant will be notified and informed of any required corrective action in the next Office action. The objection to the drawings will not be held in abeyance.
Examiner Note:
1. In bracket 1, specify the reference characters which are not found in the drawings, including the page and line number where they first occur in the specification.
2. This form paragraph may be modified to require or allow the applicant to delete the reference character(s) from the description instead of adding them to the drawing(s).
3. Unless applicant is otherwise notified in an Office action, objections to the drawings in a utility or plant application will not be held in abeyance, and a request to hold objections to the drawings in abeyance will not be considered a bona fide attempt to advance the application to final action. See 37 CFR 1.85 (a).
4. This form paragraph may be followed by form paragraph 6.27 to require a marked up copy of the amended drawing figure(s) including annotations indicating the changes made in the corrected drawings.